Federal opportunity · Solicitation
ClosedFort Lee Vehicle Recovery Range
W9123626BA006 · Dept of Defense · SAM.gov
Closed. Responses were due Oct 13, 2026, 2:00 PM ET.
- Responses due
- Oct 13, 2026, 2:00 PM ET
- Posted
- Sep 29, 2026
- NAICS code
- 236220 · Commercial and Institutional Building Construction
- Set-aside
- 8(a) Set-Aside (FAR 19.8)
- Place of performance
- Fort Lee, VA
- Notice type
- Solicitation
- Solicitation number
- W9123626BA006
- Official notice
- View on SAM.gov →
Similar open opportunities
- Trade and Cargo AcademyDept of Defense · Due Nov 6, 2026 · Under a day left
- Construction of Chilled Water Plant and Site Utility Upgrades at VA Medical Center in West Haven, CTDept of Defense · Due Nov 6, 2026 · Under a day left
- Saber FY 27-32Dept of Defense · Due Nov 6, 2026 · Under a day left
- Navy Child Development Centers (CDC) Industrialized Construction (IC) Projects via Other Transaction Authority (10 U.S.C. § 2808a)Dept of Defense · Due Nov 6, 2026 · Under a day left
- 163rd CE Flooring & Painting 2272Dept of Defense · Due Nov 6, 2026 · Under a day left
- Building 143 Concrete Scale Pad Expansion and Dock Leveler ReplacementDept of Defense · Due Nov 9, 2026 · 2 days left
What the agency was buying
Note: Please see amendment 0006 for the final drawings and specifications. Amendment 0007: An amendment has been made to Solicitation W9123626BA0006. Please see attachment SF30, Solicitation Amendment W9123626BA006_0007, extending the bid due date and bid opening date. The purpose of this project is to construct 24 concrete turning pads, along with required site drainage improvements and road alignment and repair as necessary.
The contract will be executed in three distinct phases, with the contractor granted access to only one phase at a time. Completion of each phase is required before proceeding to the next. The remaining phases (two and three) will only be performed if the options for phases are exercised.
During construction activities in one phase, the Army will conduct training operations in the remaining two phases. Each turning pad, as identified in the project drawings, will require excavation of the existing roadbed and placement of concrete in accordance with the design specifications. Storm drainage systems will be installed to ensure positive site drainage throughout the construction process.
Upon proper curing of the concrete turning pads, the connecting roads will be regarded and aligned to seamlessly integrate with the pads, as detailed in the contract drawings.
From the official notice on SAM.gov.